Global Battery Materials Tests 22-Tonne Electric Haul Truck
Electrifying off-road heavy equipment requires major capital commitments and carries significant operational uncertainty. Before reopening its Ontario site, the operator is validating digital simulations against real-world duty cycles.
A weeklong field trial is underway at the Kearney graphite mine in Ontario, led by MEDATech Engineering with support from Green Graphite Technologies. The study assesses a battery-electric vehicle (BEV) vocational haul truck rated for a 22-tonne (48,502 lb.) payload under active mining conditions.
Funded by Natural Resources Canada’s Energy Innovation Program, the feasibility project focuses on three operational pillars:
- correlating real-world haulage telemetry with digital performance models;
- measuring battery capacity, energy consumption, and site charging requirements;
- evaluating operating costs and emissions profiles ahead of a targeted 2028 mine restart.
“By pairing operational data gathered at Kearney with digital modelling, we can better understand the links between truck configuration, battery capacity, charging requirements and the mine’s production demands,” explains Rob Rennie, President and CEO of MEDATech Engineering.
MEDATech will publish a detailed case study following the trial, with partners scheduled to present their findings at a Canadian Institute of Mining, Metallurgy and Petroleum (CIM) webinar in April 2027. These validated metrics will give heavy-duty and specialty fleet managers a reliable blueprint to de-risk future electrification investments.